Income statement, headline items
Original budget, adjusted budget and audited actual side by side; each is its own figure
| Financial year | Item | Original budget | Adjusted budget | Audited actual |
|---|---|---|---|---|
| 2025/26 | Total Revenue (excluding capital transfers and contributions) | R 2 898 508 758 | R 2 795 430 308 | — |
| Total Expenditure | R 2 762 021 080 | R 2 664 875 818 | — | |
| Surplus/(Deficit) | R 136 487 678 | R 130 554 490 | — | |
| 2024/25 | Total Revenue (excluding capital transfers and contributions) | — | — | R 2 177 424 283 |
| Total Expenditure | — | — | R 3 564 485 756 | |
| Surplus/(Deficit) | — | — | −R 1 387 061 473 | |
| 2023/24 | Total Revenue (excluding capital transfers and contributions) | — | — | R 2 575 440 000 |
| Total Expenditure | — | — | R 3 260 953 182 | |
| Surplus/(Deficit) | — | — | −R 685 513 182 | |
| 2022/23 | Total Revenue (excluding capital transfers and contributions) | — | — | R 1 979 688 221 |
| Total Expenditure | — | — | R 2 396 663 639 | |
| Surplus/(Deficit) | — | — | −R 416 975 418 |
Unauthorised, irregular, fruitless and wasteful expenditure
As the municipality reported it; not a finding of wrongdoing by itself
| Year | Unauthorised | Irregular | Fruitless and wasteful |
|---|---|---|---|
| 2023/24 | R 1,0 billion | R 209 million | R 158 million |
| 2022/23 | R 0 | R 280 million | R 138 million |
| 2021/22 | R 0 | R 49 million | R 74 million |
| 2020/21 | R 0 | R 34 million | R 46 million |
| 2019/20 | R 0 | R 36 million | R 48 million |
| 2018/19 | R 0 | R 13 million | R 29 million |
| 2017/18 | R 36 million | R 22 million | R 25 million |
| 2016/17 | — | R 29 million | R 16 million |
Audit opinions
The Auditor-General's opinion on the annual financial statements, per year
| Year | Opinion | Report |
|---|---|---|
| 2023/24 | Qualified | Audit report (external site) |
| 2022/23 | Disclaimer of opinion | Audit report (external site) |
| 2021/22 | Disclaimer of opinion | not linked |
| 2020/21 | Adverse opinion | Audit report (external site) |
| 2019/20 | Unqualified - Emphasis of Matter items | not linked |
| 2018/19 | Unqualified - Emphasis of Matter items | not linked |
| 2017/18 | Unqualified - Emphasis of Matter items | Audit report (external site) |
| 2016/17 | Unqualified - Emphasis of Matter items | not linked |
| 2015/16 | Unqualified - Emphasis of Matter items | Audit report (external site) |
| 2014/15 | Unqualified - Emphasis of Matter items | Audit report (external site) |
| 2013/14 | Unqualified - Emphasis of Matter items | Audit report (external site) |
| 2012/13 | Unqualified - Emphasis of Matter items | not linked |
| 2011/12 | Unqualified - Emphasis of Matter items | Audit report (external site) |
| 2010/11 | Unqualified - Emphasis of Matter items | Audit report (external site) |
Capital expenditure by type
Latest audited year with figures; original and adjusted budgets beside the audited actual
| Type | Original budget | Adjusted budget | Audited actual |
|---|---|---|---|
| Deprecation | R 172 million | — | R 178 million |
| New | R 159 million | — | R 205 million |
| Renewal | R 7,5 million | — | R 4,4 million |
| Repairs and maintenance | R 8,4 million | — | R 31 million |
| Upgrading | R 21 million | — | R 8,7 million |
Conditional grants
Largest grant budgets in the latest year published (Treasury publishes budgets, not audited receipts, here)
| Grant | Adjusted budget |
|---|---|
| Municipal Infrastructure Grant | R 68 million |
| Integrated National Electrification Programme (Allocation in-kind) Grant | R 51 million |
| Municipal Disaster Recovery Grant | R 21 million |
| Local Government Financial Management Grant | R 1,7 million |
| Sport, Arts and Culture | R 15 million |
| Housing and Local Government | R 12 million |
| Expanded Public Works Programme Integrated Grant (Municipality) | R 1,2 million |
| Integrated National Electrification Programme (Municipal) Grant | R 10 million |
- capital
- 2017/18 – 2025/26
- conditional grant
- 2012/13 – 2018/19
- income expenditure
- 2017/18 – 2025/26
- uifw expenditure
- 2011/12 – 2023/24
Tender notices by the municipality
Where the municipality publishes on the eTender portal under its demarcation name
Why no ward figures
National Treasury reports municipal finance for the municipality as a whole. Mandate SA shows it at that level and never divides it across wards; a ward’s page links here instead.