Durban high court

Expansion of accommodation

Total budget, as stated
R 903 million
Projected budget, as stated
R 70 million
Audited outcomes to date
R 601 million

Budget and spending by financial year

Each figure keeps the kind the budget gives it; an estimate is never shown as spending

Figures by financial year
Financial yearAudited outcomeAdjusted appropriationMTEF estimate
2021/22R 170 223 000——
2022/23R 210 204 000——
2023/24R 220 656 000——
2024/25—R 218 999 000—
2025/26——R 70 000 000
2026/27——R 432 000

Procurement and contracts

Links between this project and tender notices, awards or contracts

The infrastructure feed names no tender, award or contract for its projects, and no official source on the record links this project to a procurement case by identifier. Mandate SA does not match projects to tenders on names or amounts; where a source states the relationship, it will appear here. Tenders of the owning department are listed on its record.

Who delivers it, and who claims it

The documented owner first; party claims are shown as claims, beside the evidence

Responsible department, as the infrastructure feed states it: Justice and Constitutional Development